Artsolute Media Group · Project Schedule · Rev 4 — Jul 16, 2026
Sequence per Delta Facilities (Cindy, 7/16): the AI POD moves in first, then AMG builds the Datacenter and Telecom sections around the machine. AMG installs the remaining sections in parallel while the POD moves in, and finishes by the beginning of September. Amber items are owned by Delta or the GC and are unconfirmed.
| Phase | Dates | Duration | Status |
|---|---|---|---|
| Production drawings to GC AMG → GC |
Mon Jul 13 | — | Done Delivered at Monday's GC meeting. |
| Updated CAD files to GC AMG |
Mon Jul 20 | — | GC's additional request. AMG committed to this date — nothing on the GC side moves without it. |
| Permit submittal + City of Fremont review GC / architect |
submittal TBD | review time unknown | Not submitted The review clock has not started. All fixed on-site construction waits on this — it is the project's critical path. Submittal date + expedite options needed from the GC/architect now. |
| GC construction & space handover General Contractor · gated by permit |
→ Fri Aug 21 | ~2 weeks after permit — assumed | GC to confirm Space must hand over by Aug 21 for AMG's Aug 24 move-in — which holds only if the permit clears around Aug 7. Ask GC for a section-by-section schedule with Datacenter + Telecom first. |
| Fabrication & procurement AMG shop |
now → Fri Aug 21 | ~5 weeks | Runs parallel to GC construction; everything ship-ready before move-in. |
| AI POD move-in + install Delta team · goes in FIRST |
Mon Aug 24 → Fri Aug 28 | within the week — assumed | Delta to confirm Per Delta Facilities the POD moves in before the Datacenter + Telecom sections are built. It must be in place by Fri Aug 28 for the dates below to hold. |
| Move-in Phase 1 — remaining sections AMG crew · parallel with POD move-in |
Mon Aug 24 → Fri Aug 28 | 1 week | AMG works the other areas while Delta lands the POD — no idle week. |
| Move-in Phase 2 — Datacenter + Telecom AMG crew · built around the POD |
Mon Aug 31 → Fri Sep 4 | 1 week | AMG scope complete Fri Sep 4 — meets Delta's "beginning of September" ask, and clears before the Alibaba blackout. |
| Alibaba show + dismantle AMG crew blackout |
Wed Sep 9 → Fri Sep 11 | 3 days | Fixed No showroom work scheduled. (Mon Sep 7 = Labor Day.) |
| Punch list · install support · buffer AMG + Delta |
Mon Sep 14 → Fri Sep 25 | 2 weeks | Absorbs Delta install overrun and detailing before the hard deadline. |
| Showroom ready Milestone |
Wed Sep 30 | — | Hard Management target from Delta (Cindy Lin, 5/4). |
The POD now sits upstream of AMG's Datacenter + Telecom build — its arrival date drives AMG's completion, not the other way around. Space is available from Mon Aug 24 (GC handover Aug 21, permit permitting).
| POD in place by | What the schedule looks like | Verdict |
|---|---|---|
| Fri Aug 28 the plan |
AMG builds Datacenter + Telecom around the POD Aug 31 – Sep 4 and is fully done Sep 4. Nearly four weeks of buffer to Sep 30. | Best case |
| Fri Sep 4 one week late |
Datacenter + Telecom build collides with the Sep 9–11 blackout and slides to Sep 14–18. AMG completion ~Sep 18; the "beginning of September" target is gone but Sep 30 still holds. | Tight |
| Fri Sep 11 two weeks late |
Build runs Sep 14–18, punch list eats the remaining week. AMG done ~Sep 25 with days of float left before the hard deadline. | Zero float |
| After Sep 14 — |
Datacenter + Telecom can no longer finish in front of Sep 30 without overtime or scope triage. Needs an executive conversation, not a schedule tweak. | 9/30 at risk |
The permit has not been submitted, so the City of Fremont review clock has not started. Working backwards: AMG done Fri Sep 4 → move-in starts Mon Aug 24 → GC hands over Fri Aug 21 → with ~2 weeks of GC construction, the permit must be approved around Fri Aug 7. Whether that is achievable depends entirely on when the submittal goes in and how fast the city reviews — both unknown today.
What softens the blow: AMG's fabrication is off-site and permit-independent (ship-ready Aug 21 regardless), and freestanding elements can be placed without a building permit. But two dates now sit upstream of everything: the permit submittal (GC/architect — gates the Aug 21 handover) and the POD arrival (Delta — gates the Datacenter + Telecom build). A week of slip on either collides with the Sep 9–11 Alibaba blackout; two weeks puts Sep 30 itself at risk.